The purpose of this report is to provide an
update to the Executive on the progress of the Bridgewell Supported
Living project. The project was previously approved for delivery by
Executive on 21 June 2022. Further decision is required relating to
the capital cost of the building works and the re-approval of the
strategic procurement plan for the procurement of the a) landlord
service provider and b) the care & support service
provider.
Decision type: Key
Reason Key: Expenditure >£400,000 & Affects more than 1 ward.;
Decision status: Recommendations Approved
Wards affected: Hanworth;
Notice of proposed decision first published: 30/08/2023
Anticipated restriction: Part exempt - View reasons
Explanation of anticipated restriction:
Information relating to financial or business affairs.
Decision due: 17 Oct 2023 by Executive
Lead member: Executive Member for Adult Services, Health and Housing
Lead director: Executive Director: People
Department: People
Contact: Melanie O'Rourke, Assistant Director: Adult Social Care Email: Melanie.O'Rourke@bracknell-forest.gov.uk.
Consultation process
Pre-planning application public
consultation.
Meetings and email consultation with key partners.
Consultees
At the relevant stages of the project
consultation will be undertaken during the course of this
project.
Making Representations: In writing to the Executive Director: People
Financial Impact: This project will provide new fit for purpose accommodation, which will enable efficiency in the supported care delivery. By investing in good quality home styled accommodation, the Council will continue to demonstrate its commitment to ensuring that people are supported to be independent, resilient, physically and emotionally healthy. It will also lead to net revenue savings over the long term.
Reason the item will considered in private: a. The report will contain building contractor's commercially sensitive information. b. Strategic procurement plan for the landlord service provider and the care & support service provider.