1 That the change in quantum and mix of affordable units on the site from c56% as set out in the Settled Site Development Plan to c48% be approved, noting that this still significantly exceed the required 25% of affordable housing;
2 That the Executive Director: Resources be authorised to release funding for the scheme in line with the proposed revised phased cashflow approach, noting that this does not financially disadvantage the Council.