37 Bridgewell Supported Living PDF 8 MB
To provide an update on the progress of the Bridgewell Supported Living project. The project was previously approved for delivery by Executive on 21 June 2022. Further decision is required relating to the capital cost of the building works and the re-approval of the strategic procurement plan for the procurement of the landlord service provider and the care & support service provider.
Additional documents:
Minutes:
RESOLVED that:
i. the progress to date on the design development is noted and the timetable in
paragraph 5.27 is agreed.
ii. the value improvement items to improve sustainability in paragraphs 5.11 is noted.
iii. the revised strategic procurement plan for appointment of the provider of
landlord services (Housing Association) and care services (Support Provider) for the provision of Bridgewell Supported Living scheme for adults with learning disabilities as laid out in paragraphs 5.16 to 5.20 are noted.
RECOMMENDED to Council to approve the additional cost of works for the new
accommodation by £400k, changing the previous budget from £7.15m to £7.55m as
detailed in paragraph 5.12.