Highways and Transport Capital Programme 2024/25

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the Highways and Transport Capital Programme for 2024/25 and its implementation as set out within the report.

Decision:

RESOLVED that the Highways and Transport Capital Programme for 2024/25 is approved.

Reasons for the decision:

The proposals seek to facilitate transport in line with the council’s Local Transport Plan 3 (LTP3) and ensure that the highway is maintained in as good a condition as resources allow, having due regard to the council’s intervention policy based on network condition

Alternative options considered:

       i.         Failure to approve the Highways and Transport Capital Programme would prevent the delivery of the council’s obligations as a Highway Authority and be contrary to the position set out in the council’s adopted Transport Policy (LPT3).

 

     ii.         Given the demands placed upon highway maintenance funding levels in previous years, it would not be appropriate to allocate resources to anything other than the priorities identified through methodical and objective needs assessments.

Interests and Nature of Interests Declared:

None

Reason Key: Affects more than 1 ward;

Wards Affected: (All Wards);

Financial Impact: The report identifies specific schemes on which funding is to be allocated.

Declarations: None

Subject to Urgent Proceedings: No

Making Representations: In writing to the Executive Director: Place, Planning and Regeneration

Other reasons / organisations consulted

Stakeholders will vary dependent on individual schemes and their impact. Applicable consultation processes will precede scheme implementation.

Consultees

Subject to individual scheme.

Contact: Neil Mathews, Assistant Director: Highways and Transport Email: neil.mathews@bracknell-forest.gov.uk Tel: 01344 351163.

Report author: Neil Mathews

Publication date: 19/03/2024

Date of decision: 19/03/2024

Decided at meeting: 19/03/2024 - Executive

Effective from: 27/03/2024