Decision details

Capital Programme Outturn 2015/16

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To note outturn expenditure and financing and to approve carry forwards.

Decision:

1.    That the outturn capital expenditure be noted, in particular the key variances identified in paragraph 5.5 of the report

2.    That the carry forward of £20.967m from the 2015/16 capital programme to 2016/17 including £0.339m relating to projects approved in 2014/15 be approved. (see paragraph 5.6 of the report)

3.    That the financing of capital expenditure as detailed in Table 2 of the report be noted.

4.    That the additions and virements to the 2016/17 Capital Programme be approved as outlined in paragraphs 5.14 to 5.18 of the report.

Reasons for the decision:

The reasons for the recommendations are set out in section 5 of the report.

Alternative options considered:

Not applicable.

Reason Key: Expenditure > £400,000;

Wards Affected: (All Wards);

Financial Impact: None at this time

Declarations: None.

Subject to Urgent Proceedings: No.

Making Representations: In writing to the Borough Treasurer

Other reasons / organisations consulted

None

Consultees

N/A

Contact: Calvin Orr, Head of Finance & Business Services Email: calvin.orr@bracknell-forest.gov.uk Tel: 01344 352125.

Report author: Calvin Orr

Publication date: 18/07/2016

Date of decision: 18/07/2016

Decided at meeting: 18/07/2016 - Executive

Effective from: 26/07/2016