The purpose of this report is to provide an
update on the progress of the Blue Mountain Community and Health
Care Hub scheme and the supporting financial summary. The project
is in partnership with the East Berkshire Clinical Commissioning
Group (CCG). A decision is required to proceed to the next stage of
the project, which includes completion of the heads of terms,
appointment of a design team for completion of RIBA Stage 3 design
and applying for planning permission. The CCG submitted an outline
business case to the NHS in July 2019 to secure funding for the
health provision. A procurement plan tailored to the specific
requirements of this project requires approval.
Decision type: Key
Reason Key: Expenditure > £400,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 02/08/2019
Anticipated restriction: Part exempt - View reasons
Explanation of anticipated restriction:
Paragraph 3 - Information relating to financial or business affairs.
Decision due: 17 Dec 2019 by Executive
Lead member: Executive Member for Culture, Delivery and Public Protection
Lead director: Executive Director: Place, Planning & Regeneration
Department: Place, Planning & Regeneration
Contact: Andrew Hunter, Executive Director: Place Email: andrew.hunter@bracknell-forest.gov.uk Tel: 01344 351907.
Consultation process
Meetings and email consultation with key
partners.
Consultees
East Berkshire CCG (and health service
providers via the CCG), Binfield Parish Council.
Making Representations: In writing to the Director: Place, Planning & Regeneration
Financial Impact: The Council has a legal obligation to provide community facilities at the Blue Mountain site. The proposal requires capital funding for the proposed new facilities including a contribution from the NHS.
Reason the item will considered in private: Paragraph 3 - Information relating to financial or business affairs.