i. The High Street Car Park be closed at the end of October 2023, following the
recommendation made by Structural Engineers.
ii. The Assistant Director, Property engages with stakeholders affected which
includes the commercial unit tenants (9), Council staff, season ticket holders, Town Centre partners and other parties that have an interest to ensure the implications of this decision are understood.
iii. Savings that will be realised in expenditure budgets in the current year from the midyear closure be used to fund decommissioning work including erecting hoarding, securing the site, and commissioning pre and post decommissioning structural surveys.
iv. The High Street Car Park site be added to the Bracknell Town Centre Southern Gateway site masterplan area. Outline plans for which will be presented for consideration to the Executive in Autumn 2023.