RESOLVED that

 

        i.         option B - Council to build two-storey building with four distinct households consisting of 5-bedrooms (total 20-beds). The Council to procure a) the landlord service provider and b) the care & support service provider is approved.

 

       ii.         the design and build budget is approved.

 

      iii.         the Strategic Procurement Plan for the building design and works (including early/enabling works) in Appendix 3 is approved.

 

     iv.         the Strategic Procurement Plan for the a) landlord service provider and b) the care & support service provider in Appendix 4 is approved.

 

      v.          the timetable set out in paragraph 5.23 is approved.