Procurement Plan for Environmental Monitoring

Meeting: 15/03/2022 - Executive (Item 242)

242 Procurement Plan for Environmental Monitoring pdf icon PDF 11 KB

That the Procurement plan for the Environmental Monitoring Contract tender is approved. The current contract has been in place since 2011 and following an extension granted in 2016 the contract must now be re-tendered.

Additional documents:

Minutes:

RECOMMENDED to the Executive Member for the Environment that:

 

1.     The Strategic Procurement Plan for Environmental Monitoring services is approved.

2.     Authority is delegated for the contract award decision to the

Executive Director, Delivery and Executive Member for the Environment.

3.     The subsequently delegate authority for enacting the permitted contract extension to the Executive Director, Delivery.