Blue Mountain Community and Health Care Hub

Decision Maker: Executive Director: Place, Planning & Regeneration, Executive Member for Adult Services, Health and Housing, Executive Member for Culture, Delivery and Public Protection

Decision status: Recommendations Approved (subject to call-in)

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The purpose of this report is to approve the main works contract for the construction of the Blue Mountain Community and Health Care Hub in line with the procurement plan, and to note the partnership arrangements with the Frimley Clinical Commissioning Group (CCG) as per the draft Project Agreement (Addendum). A procurement plan tailored to the specific requirements of this project was approved by the Executive in December 2019.

Decision:

That the Executive Director: Place, Planning & Regeneration in consultation with the Executive Member:

 

       i.         Approves the award of a contract for the main works for the Blue Mountain Community and Health Care Hub redevelopment within the budget approved by the Executive in October 2021, the contract sum for the main works is set out in Appendix A.

 

     ii.         Agree that the Council continues to work in partnership with the Frimley Clinical Commissioning Group by entering into a project agreement (addendum) for the next stage, which is included in Appendix C.

Reasons for the decision:

The Executive approved at its meeting on 19 October 2021 to approve the community centre budget and agreed to forward fund including ancillary costs), the capital costs of the Health part of the building, on the basis that the consequent capital financing costs will be covered by any capital contributions secured by the CCG and/or the long-term rental income from the Health provider.

Alternative options considered:

The design and cost plan has been developed through the pre-construction services agreement using the London Construction Framework for a two-stage tendering process. Alternatively, the Council could procure the works stage contract by organising a new procurement exercise but this would lead to significant delay in meeting the requirements for the health funding.

Interests and Nature of Interests Declared:

None

Reason Key: Expenditure > £400,000;

Wards Affected: Binfield with Warfield;

Financial Impact: The Council has a legal obligation to provide community facilities at Blue Mountain. The proposal requires capital funding for the proposed new facilities including a contribution from the NHS.

Declarations: None

Subject to Urgent Proceedings: Yes

Making Representations: In writing to the Executive Director: Place, Planning & Regeneration.

Other reasons / organisations consulted

Meetings and email consultation with key partners.

Consultees

Binfield Parish Council, Frimley CCG (and health service providers via the CCG), Binfield Community (pre-planning consultation).

Contact: Andrew Hunter, Executive Director: Place Email: andrew.hunter@bracknell-forest.gov.uk Tel: 01344 351907.

Urgent item?: Yes

Publication date: 08/11/2021

Date of decision: 08/11/2021

Date comes into force if not called in: 09/11/2021

Call-in deadline date: 08/11/2021

  • Restricted enclosure  View reasons restricted
  • Restricted enclosure  View reasons restricted
  • Restricted enclosure  View reasons restricted
  • Restricted enclosure  View reasons restricted
  •  

    Contact Information

    Democratic services

    Email: committee@bracknell-forest.gov.uk