Issue - decisions

The Blue Mountain Programme: Delivery Strategy for the Learning Village and Community Facilities

21/10/2014 - The Blue Mountain Programme: Delivery Strategy for the Learning Village and Community Facilities

That:

 

         i.            the scope and programme for Blue Mountain Learning Village as per paragraphs 5.12 and 5.13 of the Chief Executive’s report be approved.

 

       ii.            the funding model as per Appendix 3 of the Chief Executive’s Report for the delivery of the Learning Village after noting the dependencies and risks (paragraphs 5.14 to 5.39 of the Chief Executive’s report) be agreed

 

      iii.            the site acquisition in principle with the land owner of the Blue Mountain site as laid out in Appendix 4  of the Chief Executive’s report subject to the due diligence to be completed by the Council’s property and legal team be approved   

 

     iv.            the Leader be requested to arrange that the decision relating to the terms of acquisition (and disposal) of land at Blue Mountain be taken by the Executive Member for Transformation and Finance.

 

      v.            the Procurement Plan in Appendix 2 of the Chief Executive’s report for the use of the Improvement Efficiency South East (IESE) framework to procure the contractor for pre-construction services and main works for the Learning Village be approved