Agenda item

20/00031/COND 28 Meadow Way, Bracknell, Berkshire

Details pursuant to Condition 03 (Materials), Condition 04 (Slab Levels), Condition 08 (Landscaping), Condition 09 (Boundary Treatments), Condition 10 (Sustainability Statement), Condition 17 (Site Organisation) and Condition 23 (Services) of planning permission 17/00929/FUL.

 

Minutes:

Details pursuant to Condition 03 (Materials), Condition 04 (Slab Levels), Condition 08 (Landscaping), Condition 09 (Boundary Treatments), Condition 10 (Sustainability Statement), Condition 17 (Site Organisation) and Condition 23 (Services) of planning permission 17/00929/FUL.

 

The Committee noted:

·         The supplementary report tabled at the meeting.

·         The objections received from 8 postal addresses as detailed in the agenda.

·         The further objection received as detailed in the supplementary report.

 

RESOLVED that the details submitted in respect of conditions 3, 4, 8, 9, 10, 17 and 23 of planning permission 17/00929/FUL, and as listed below, are APPROVED:

 

Condition 3 - materials

The use of the following materials are acceptable:

Roof tiles - Redland plain concrete tiles.

Facing brickwork - Wienerberger multi-clay bricks.

Feature diaper pattern brickwork - Wienerberger blue.

Render - K-Rend (Silicone coloured render).

Windows and doors - Eurocell UPVC in slate grey.

Rainwater goods - gutters and downpipes in anthracite grey.

The development shall be carried out in accordance with the approved details.

 

Condition 4 - slab levels

The details shown on drawing no. 17-03-PL-601-B received 20 February 2020 and drawing no. E02 Rev A received 12 January 2021 are acceptable in relation to the above condition.

The development shall be carried out in accordance with the approved details.

 

Condition 8 - landscaping

The details shown on drawing nos. 17-03-WD-101 E, 10105.01 Rev A, 10105.02 Rev A and E02 Rev A received 26 May 2020, 8 September 2020 and 12 January 2021 and document entitled Maintenance and Management Plan - soft works and hard works received 20 February 2020 are acceptable in relation to the above condition.

All planting comprised in the soft landscaping works shall be carried out and completed in full accordance with the approved scheme, in the nearest planting season (1st October to 31st March inclusive) to the completion of the development or prior to the occupation of any part of the approved development, whichever is sooner. All hard landscaping works shall be carried and completed prior to the occupation of any part of the approved development.

 

Condition 9 - boundary treatment

The details shown on drawing nos. 17-03-WD-101 E, and 10105.01 Rev A received 26 May 2020 and 8 September 2020 are acceptable in relation to the above condition.

The approved scheme shall be implemented in full before the occupation of the new dwellings and retained as such thereafter.

 

Condition 10 - sustainability

The details contained in document entitled "Appendix AA - Water Efficiency Calculator for new dwellings" received 20 February 2020 are acceptable in relation to the above condition.

The development shall be implemented in accordance with the approved details and retained as such thereafter.

Condition 17 - site organisation

The details shown on drawing nos. 17-03-PL-801-D and 17-03-PL-901-A received 16 December 2020 are acceptable in relation to the above condition.

Each facility shall be retained throughout the course of construction of the development, free from any impediment to its designated use. No other areas on the site, other than those in the approved scheme shall be used for the approved purposes.

 

Condition 23 - services

The details contained in the document “Arboricultural Method Statement” (Rev C) by Barton Hyett Associates received 12 January 2021 and shown on drawing no. 404-S-01 Rev H received 15 December 2020 are acceptable in relation to the above condition.

 

The development shall be carried out in accordance with the approved details.

 