Agenda item

18/01059/FUL 12 Greenways, Sandhurst, Berkshire GU47 8PJ

Erection of single storey front, side and rear extensions and alterations to materials.

Minutes:

Erection of single storey front, side and rear extensions and alterations to materials.

 

The Committee noted:

 

·         The supplementary report of the Head of Planning tabled at the meeting.

·         Sandhurst Town Council raised no objections to the application.

·         Five letters of objection received from residents, as summarised in the Agenda papers.

 

RESOLVED that the application be APPROVED subject to the following

conditions:-

 

01.       The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

REASON: To comply with Section 91 of the Town and Country Planning Act 1990.

 

02.       The development hereby permitted shall be carried out only in accordance with the following approved plans and other submitted details, received 29th January 2019 by the Local Planning Authority:

OS Plan and Proposed Site Plan – Drawing Number: GA001 A

Proposed Site Plan – Drawing Number: GA004 C

Proposed Ground Floor Plan – Drawing Number: GA005 B

Proposed Roof Plan – Drawing Number: 007 C

Proposed Elevations – Drawing Number: GA015 D

REASON: To ensure that the development is carried out only as approved by the Local Planning Authority.

 

03.       No works shall take place until samples of the materials to be used in the

construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the Local Planning Authority. The works to the development shall be carried out in accordance with the approved details.

REASON: In the interests of the visual amenities of the area.

[Relevant Policies: BFBLP EN20, Core Strategy DPD CS7]

 

04.       The tree/ vegetation protection measures shown on the approved site plan shall be erected in accordance with BS 5837:2012 (or any subsequent revision) Section 6 prior to the commencement of development, including any initial clearance, and shall be maintained fully intact and (in the case of the fencing) upright until the completion of all building operations on the site. No activity of any description must occur at any time within these areas including but not restricted to the following: -

a) No mixing of cement or any other materials.

b) Storage or disposal of any soil, building materials, rubble, machinery, fuel,

chemicals, liquids waste residues or materials/debris of any other description.

c) Siting of any temporary structures of any description including site office/sales buildings, temporary car parking facilities, porta-loos, storage compounds or hard standing areas of any other description.

d) Soil/turf stripping, raising/lowering of existing levels, excavation or alterations to the existing surfaces/ ground conditions of any other description.

e) Installation/siting of any underground services, temporary or otherwise

including; drainage, water, gas, electricity, telephone, television, external lighting or any associated ducting.

f) Parking/use of tracked or wheeled machinery or vehicles of any description.

In addition to the protection measures specified above,

a) No fires shall be lit within 20 metres of the trunks of any trees or the centre line of any hedgerow shown to be retained.

b) No signs, cables, fixtures or fittings of any other description shall be attached to any part of any retained tree.

REASON: - In order to safeguard trees and other vegetation considered to be worthy of retention in the interests of the visual amenity of the area.

[Relevant Policies: BFBLP EN1 and EN20, CSDPD CS7]