Issue - meetings

Winter Preparations

Meeting: 10/01/2012 - Environment, Culture and Communities Overview & Scrutiny Panel (Item 34)

Winter Preparations

A brief oral update in respect of  the preparations for treatment of highways during the winter will be provided.

Minutes:

The Chief Officer: Environment and Public Protection gave a brief oral update on winter preparations. The salt barn held 3000 tons of salt, of which 150 tons had been used this winter.  The gritting vehicles had moved to Downmill Road and extra equipment had been purchased at a cost of £70k.

 

The Panel noted that the salt would be fine as long as it was stored dry.  However if it did become unusable it was the contractor’s responsibility to replace it.