Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To approve the award of contract for the Cranbourne additional classrooms works.
That the contract for the construction works for the new classrooms at Cranbourne Primary School under the Education Capital Programme, previously approved by the Executive, be awarded to Tenderer A as detailed in Appendix A of the Director of Children, Young People and Learning’s report, subject to the final lump sum not exceeding the amount set out in paragraph 18 of the restricted Appendix A attached to the Director of Children, Young People and Learning’s report
The value of this contract requires Executive approval under the Council’s Contract Standing Orders.
Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
None
Reason Key: Expenditure > £400,000;
Corporate Priorities : To improve outcomes for children and young people.;
Wards Affected: Winkfield & Cranbourne;
Financial Impact: Within existing budget
Declarations: None
Subject to Urgent Proceedings: No
Making Representations: In writing to the Director of Children, Young People & Learning
Other reasons / organisations consulted
Meetings with interested parties
Consultees
Cranbourne School, Education Capital Programme Board
Contact: David Watkins, Chief Officer: Strategy, Resources and Early Intervention Email: david.watkins@bracknell-forest.gov.uk Tel: 01344 354061.
Report author: David Watkins
Publication date: 23/09/2014
Date of decision: 23/09/2014
Decided at meeting: 23/09/2014 - Executive
Effective from: 01/10/2014
Accompanying Documents: