Decision Maker: Education Capital Programme Contracts Committee
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To award the contract for the Brakenhale
School Phase 4 works.
That the contract for the construction works for the final Phase 4 of the expansion of The Brakenhale School be awarded to Tenderer A as set out in section 25 of the attached Restricted Appendix A.
The value of this contract requires Executive approval under the Council’s Contract Standing Orders.
The recommended tender is affordable within the budget previously approved by the Executive
The Phase 4 works form part of a masterplan for the expansion of The Brakenhale School in which various options for the expansion works were considered.
None.
Reason Key: Expenditure > £400,000;
Corporate Priorities : To improve outcomes for children and young people.;
Wards Affected: Old Bracknell;
Financial Impact: Within existing budget
Declarations: None.
Subject to Urgent Proceedings: The Education Capital Programme Contracts Committee was established to determinbne this matter to enable a quicker procedure than would have been possible given the existing schedule of meetings of the Executive.
Making Representations: In writing to the Director of Children, Young People & Learning
Other reasons / organisations consulted
Meetings with interested parties
Consultees
Headteacher
School Governing Body
Education Capital Programme Board
Contact: David Watkins, Chief Officer: Strategy, Resources and Early Intervention Email: david.watkins@bracknell-forest.gov.uk Tel: 01344 354061.
Publication date: 01/08/2014
Date of decision: 29/07/2014
Effective from: 07/08/2014