Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To award the contract for the capacity works
at The Pines Primary school
That the contract for Phase 1 of the expansion of the Pines Primary School be awarded to Tenderer A, as detailed in the confidential appendix A of the Director of Children, Young People and Learning’s report, subject to the final lump sum not exceeding the amount set out in paragraph 13 h of the report.
The value of this contract requires Executive approval under the Council’s Contract Standing Orders.
None at this time.
None
Reason Key: Expenditure > £400,000;
Corporate Priorities : To improve outcomes for children and young people.;
Wards Affected: Hanworth;
Financial Impact: Central Government grant
Declarations: None
Subject to Urgent Proceedings: No
Making Representations: In writing to the Director of Children Young People and Learning
Other reasons / organisations consulted
Meetings with interested parties
Consultees
Headteacher
School Governing Body
Education Capital Programme Board
Contact: David Watkins, Chief Officer: Strategy, Resources and Early Intervention Email: david.watkins@bracknell-forest.gov.uk Tel: 01344 354061.
Publication date: 24/06/2014
Date of decision: 24/06/2014
Decided at meeting: 24/06/2014 - Executive
Effective from: 02/07/2014
Accompanying Documents: