The contract for the demolition works for the
Blue Mountain Community Hub Redevelopment project has been procured
in accordance with the Council’s Standing orders and the
Procurement Plan agreed by the Executive in December 2019.
Reasons for the decision:
Confirming the results of the tenders for the
demolition of the existing building on the site of the Blue
Mountain Health Community facility site.
Alternative options considered:
Retention of the building, however, not
considered viable.
Wards Affected: Binfield with Warfield;
Other reasons / organisations consulted
None
Contact: Andrew Hunter, Executive Director: Place, Planning & Regeneration Email: andrew.hunter@bracknell-forest.gov.uk Email: andrew.hunter@bracknell-forest.gov.uk Tel: 01344 351907.
Publication date: 13/02/2020
Date of decision: 13/02/2020