Decision details

Education Capital Programme - Great Hollands Primary School Expansion

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval of the award of contract for the construction works for the expansion of Great Hollands Primary School

Decision:

That the award of contract for the construction works for the expansion of Great Hollands Primary School be awarded to Tenderer F, as detailed in the restricted appendix to the Director of Children, Young People and Learning’s report, subject to the final lump sum not exceeding the amount set out in paragraph 19 of the Restricted Appendix

Reasons for the decision:

The value of this contract requires Executive approval under the Council’s Contract Standing Orders.

 

Alternative options considered:

Great Hollands was one of eleven South Bracknell primary schools considered for expansion by the Education Capital Programme Board in 2014 and it was selected because of the schools with sufficient site area, it had a “Good” rating at Ofsted and the estimated cost was affordable.

 

A feasibility study was then undertaken of Great Hollands to identify different options for the expansion of the school buildings which has been subject to consultation and agreement with the Headteacher and Governing Body. 

 

Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.  

 

Interests and Nature of Interests Declared:

None

Reason Key: Expenditure > £400,000;

Wards Affected: Great Hollands North;

Financial Impact: Within existing funding

Declarations: None

Subject to Urgent Proceedings: No

Making Representations: In writing to the Director of Children, Young People and Learning.

Other reasons / organisations consulted

Meetings with the school, Governing Body and the Education Capital Programme Board.
Public consultation held in July 2015.

Consultees

Headteacher, Governing Body, parents, local neighbours/residents.

Contact: David Watkins, Chief Officer: Strategy, Resources and Early Intervention Email: david.watkins@bracknell-forest.gov.uk Tel: 01344 354061.

Report author: David Watkins

Publication date: 26/01/2016

Date of decision: 26/01/2016

Decided at meeting: 26/01/2016 - Executive

Effective from: 03/02/2016